April 2019

  • At the April 8, 2019 meeting, Mrs. Heverly Flesher reviewed an amendment to the agreement with K&W for a traffic study for the new construction for the middle school. This was added to the consent agenda forthe April 15, 2019 meeting. At the April 15 meeting, Mrs. Heverly Flesher requested approval for an addition to the original contract with Advantage Engineers. The board approved the Supplemental Geotechnical Engineering Services agreement for a price not to exceed $38,545. At a special meeting on April 29, 2019, Ken Johnson reviewed the bid results for the contractors to complete the asbestos abatement work on Brownstown Elementary School. Additionally, Don Main presented the bid results and the recommendations for bid awards for the renovation and additions to Brownstown Elementary School. The board unanimously approved both bid proposals.